Starting point

This included ordering the steel parts, pre-assembly in the Lucerne shipyard, transport to the CGN shipyard in Lausanne and assembly on site.

Challenges

Due to the very ambitious timeframe, there were less than 30 days between delivery of the steel parts to the Lucerne shipyard and completed assembly on site in the shipyard in Geneva.

Technical data 
Capacity562 people
Overall length48.5 m
Overall width9.4 m
Displacement270 t
Speed26 km/h
Drive power2x 551 kW

 

Key data 
Client / CustomerCGN SA
Propulsion driveDiesel engines
Project volume100,000 CHF
Year of completion2014
Shiptec servicesPlanning, construction and assembly